Lively Lane has been a buzz through the holidays since our last update. The new year has brought about a new phase of construction: finishes! Phase one Clever Townhomes have received their first coat of interior paint making way for cabinets, interior doors & trim, and tile installation. What began as just a collection of rough materials is … Continue reading Construction Update: Putting on the Finish
Category: Construction Update
Construction Update: Momentarily Tan
With exterior steel work mounted and siding installation nearing completion, the exterior look of each home is gaining more definition. All buildings have received exterior doors and siding, except the LiveWork building where the board & batten work is just commencing. Next up for the exterior is paint. The design team has been reviewing on site … Continue reading Construction Update: Momentarily Tan
Construction Update: Balconies on the Balcones
For the past month, most work at Lively Lane has occurred inside the walls and ceilings of each home, but there is again some visual progress on the outside too as we transition into some beautiful Texas autumn weather. If you pass by today, you’ll notice that some of the balconies and awnings – constructed … Continue reading Construction Update: Balconies on the Balcones
Construction Update: Earning Our Stripes
As the summer days are heating up, so has the activity over at Lively Lane! The exterior building envelope continues to be prepped for final siding and roof installation, and all units are nearly dried in with windows, patio doors, and protective roofing underlayment in place. Balcony construction has now started (off-site) and awnings will … Continue reading Construction Update: Earning Our Stripes
Construction Update: Literally Green Buildings!
Although this rainy summer has slowed us down a bit, our teams are continuing to make progress on the exterior building envelope here at Lively Lane. Since our last update, each building’s Zip System® sheathing (which integrates an air and water barrier too) has turned our buildings quite literally green! We’re talking about the color, … Continue reading Construction Update: Literally Green Buildings!
Construction Update: Topping Out!
Now that the May rains have (finally!) subsided, things are picking back up at Lively Lane! Framing is finishing up for Phase I homes and the outlines of our little pocket neighborhood are emerging. The exterior building envelope is now underway with sheathing installation in progress. Once this outer shell is in place, roofing, balconies, … Continue reading Construction Update: Topping Out!
Construction Update: Going Vertical
With primary building foundations in place, framing has finally begun! The first floor of all Phase I homes in the neighborhood are already complete and second floor trusses and framing are in progress. The construction team also continues to work finishing up the underground utility connections around the site, including electric, water, wastewater, stormwater, high-speed … Continue reading Construction Update: Going Vertical
Construction Update: Creating Foundations
If you’ve passed by Lively Lane lately, you’ll notice that behind our construction fencing signage (installed by our friends at FASTSIGNS), the site is busy! Read on for some brief highlights of construction activity. With site work still underway, the team has begun installing the underground water, sewer, electrical, and drainage utilities on-site and connecting each … Continue reading Construction Update: Creating Foundations
Construction Update: Breaking Ground
Dirt work began in earnest in late January after the team diligently installed erosion and sedimentation controls for construction. The site is also protected by construction fencing that will soon feature screening that will further highlight the project and the team that has joined together to bring it to life. For now, there’s a full view … Continue reading Construction Update: Breaking Ground